Rock blasting works on for 4-lane

Rock blasting works on for 4-lane
Rock blast work in progress near Pakala Pahar bridge. (DPRO)
DIMAPUR, MAY 22 (NPN) | Publish Date: 5/22/2019 11:19:51 AM IST

Intensive earth cutting works along the ongoing Dimapur-Kohima four lane project from Patkai Bridge to Pakala Pahar Bridge has entered third day.

According to a DIPR report, DC Dimapur Kevekha Kevin Zehol updating on the ongoing works informed that out of the 128 + 950 km stretch, a stretch of 129 + 300 km has been opened. Presently, the 60 metre height hill has come down to 45 metre after working for the last two nights. 

At least ten excavators along with two rock breakers and 15 dumpers are being used for carrying out the intensified works. Last night, 245 trips of rocks/soil have been transported.

DC Dimapur had earlier issued a circular restricting movement of traffic from 10:30 p.m. to 5 a.m. till June 20, 2019. 

 

Launched on December 3,1990. Nagaland Post is the first and highest circulated newspaper of Nagaland state. Nagaland Post is also the first newspaper in Nagaland to be published in multi-colour.

Desk:+91-3862-248 489, e-mail: npdesk@gmail.com Fax: +91-3862-248 500
Advt.:+91-3862-2482 267, e-mail:npostadvt@gmail.com

QUICK LINKS

SUNDAY POST

Join us on

© Nagaland Post 2018. All Rights are Reserved
Designed by : 4C Plus